thepro bulkhead

Your problem solver for large construction sites and gap filling.

The thepro bulkhead is installed in front of the shoring,
without additional costs for straightening the substrate.

thepro bulkhead mounting bar

For fixing thepro
elements vertically to the shoring

thepro insulating sealing elements (DDE)

Produced to the exact height of your cellar

thepro bulkhead spacer

To maintain the planned wall thickness when filling the cavity for shoring

thepro bulkhead U-profile

For aligned installation of thepro elements, for fastening to a clean layer

wolfseal KB 16

Metal waterstop for sealing
construction joints

thepro insulating sealing elements (DDE)

Also suitable for use under the floor slab

The 2.40 m wide elements are simply placed in a U-profile attached to the substrate (see photo 1) and then attached to the shoring using the mounting rod (see photo 2). A working space between the shoring and thepro shell is not required for this.

After the reinforcement of the floor slab has been installed, the cavity between the shoring and thepro bulkhead is filled with sand, gravel or suitable filling material up to the top edge of the floor slab.

The thepro shell is thus sturdily braced to withstand the concrete pressure of the floor slab.

1st U-profile at the base

2. mounting rod

When the wall reinforcement is installed, thepro spacers are integrated into the reinforcement in a grid of approx. 45cm / 45cm (see photo 3).

After a single-sided formwork has been closed on the inside of the wall, the remaining gap between the shoring and thepro element is also filled with gravel or suitable filling material (see photo 4).

The spacers inserted between the reinforcement are now supported against the single-sided formwork and thus ensure that the subsequent wall thickness is precisely maintained.

The concreting and stripping of the walls corresponds to the conventional working method.

thepro bulkhead spacer

3. spacer

4. filling the gap

Construction site procedure

thepro bulkhead

Take a look at the construction site process when using thepro bulkhead.

FBV waterproofing membrane, thermal insulation and formwork in one system

Saves any substrate preparation on vertical shoring

Significant time and cost savings

Suitable for exposed concrete

Mounting thepro bulkhead

Mounting thepro bulkhead

The excavation pit is prepared with a level clean layer. The planned concreting sections are taken into account using (lost) formwork (up to the outer edge of the insulation). It is also possible to install the formwork later, e.g. by tilting the formwork with the shoring.

Mounting thepro bulkhead

The U-profile must be fixed flat on the cleanliness layer (fixing not included in the scope of delivery). The high stop sash defines the outer edge of the insulation.

Mounting thepro bulkhead

The thepro elements are placed on the U-profile.

Mounting thepro bulkhead

The thepro elements are attached to the stop sash of the U-profile from the inside. The small fixing bracket presses into the thepro element and fixes it in place.

Mounting thepro bulkhead

The thepro elements are fixed in place with the mounting rods. The front part of the mounting rod is fixed to the thepro element using an insulation plug (bit: TX 40). The rear part of the mounting rod is fixed to the shoring using suitable fixing material (not included in the scope of delivery). For vertical installation, the mounting rod is adjusted to the required dimension using the split pin lock.

Mounting thepro bulkhead

Each thepro element is attached to the side with 2 mounting rods.

Mounting thepro bulkhead

In the direction of installation, the panels are mounted vertically using 2 mounting rods. On the other side, the panels are welded to the previous panel.

Mounting thepro bulkhead

The operations are repeated.

Mounting thepro bulkhead

The floor slab is conventionally reinforced. Additional spacers are installed at the front of the floor slab.

Mounting thepro bulkhead

The cavity between the shoring and thepro bulkhead is filled with gravel or single grain concrete up to the top of the floor slab.

The filling must not be compacted.

Mounting thepro bulkhead

The floor slab is concreted.

Mounting thepro bulkhead

The spacers are installed between the inner and outer reinforcement and define the exact wall thickness. The support surfaces are installed on the outside and the plastic caps on the inside. To ensure speedy installation, the spacers are supplied on rails.

Mounting thepro bulkhead

The outer reinforcement layer is installed conventionally. The spacers are then installed in a 45 cm x 45 cm grid and connected to the outer reinforcement layer (e.g. with binding wire).

Mounting thepro bulkhead

Once all the spacers have been installed, the inner reinforcement layer is installed. The spacers are also connected here. The spacer must be installed at a 90° angle to the thepro elements. The position must also be maintained under the pressure generated when backfilling the bulkhead.

Mounting thepro bulkhead

The wall is closed with single-sided formwork.

Mounting thepro bulkhead

The cavity between the shoring and thepro bulkhead is filled with gravel or single grain concrete up to the top of the wall. The filling material must not be compacted. The wall is then concreted.

Mounting thepro bulkhead

Finished concrete wall after stripping the formwork

Assembly video

thepro bulkhead

Watch a video of the installation of thepro bulkhead.

You might also be interested in

FBV Slide

Surface sealing

System description

thepro Standard construction site

thepro Standard

System description

Are you planning a building and need support with waterproofing?
Then get in touch. We are happy to support you.

Roland Wolf GmbH Bauwerksabdichtung